Hybrid power station of ENERTRAG AG

Place of construction:17291 Wittenhof, GermanyYear of construction:20112 FermentersDiameter: 21.33 m

Height: 7.07 m

Volume: 2,530 m³ each

Tank equipment: with attached gas depot, volume: 800 m³Digestate depotDiameter: 29.87 m

Height: 7.07 m

Volume: 4,950 m³

Tank equipment: with attached gas depot, volume: 2,400 m³